Week 1 & 2 progress
Weeks 1 & 2 on site comprised Site clearance, formation of new openings, erection of scaffolding for roof, façade and chimney stack restoration works, internal demolitions to the lower ground floor comprising removal of floors, walls and ceiling finishes.