Rostrevor Terrace Week 5 Progress

Works are nicely progressing to the Garden Level.

New opening has been formed between proposed Kitchen & Dining Room which will give a generous, light filled family space.

Screed poured and first fix plumbing ongoing. The existing walls have been stripped to allow for damp proofing and insulation.

Before and after images of chimney re-build and re-pointing complete to main roof structure.