Work commenced on the strip out of former World Rugby Board premises on the second floor of Huguenot House. Strip out of existing partition walls, fitted furniture, ceilings and floor finishes.

Work also commenced on the strip out of the existing power and data installations.

We were asked by the client to re-use or recycle as much of the existing materials as possible to reduce waste going to landfill. We have designed the scheme to keep in position or re-use all of the timber panelling with it being painted or covered with Tektura commercial covering in the new Boardroom and Meeting Rooms.