Clanna Gael Fontenoy GAA Club Progress

Week 4 on site at Clanna Gael Changing Room Facility renovation and fit-out. Building works are progressing at a good pace on site with new floor screeds poured throughout, new galvanised electrical and lighting containment and fire detection cabling nearing completion, new walls are all prepared for metal and whiterock cladding.

Fabrication of the bespoke metalwork well underway too. New raw mild steel benches, coat hooks lettering and numbering all nearing completion with installation due to commence next week.

Installation of new floor and wall finishes is due to commence next week along with mechanical works and painting and decoration.