Huguenot House Key Capital Fit-out (Week 5 Progress)

Phase 1 almost complete, due for handover to client on Monday 1st June. Carpets almost completely installed, glazed partitioning almost complete, painting complete window blinds installed, second fix electrical, data and lighting complete. The colour scheme has been kept clean, fresh and bright as the furniture is quite dark in colour (Applewood) with black chairs. Phase 2 […]

Huguenot House Key Capital Fit-out (Week 1 Progress)

Work commenced on the strip out of former World Rugby Board premises on the second floor of Huguenot House. Strip out of existing partition walls, fitted furniture, ceilings and floor finishes. Work also commenced on the strip out of the existing power and data installations. We were asked by the client to re-use or recycle […]