Works are nicely progressing to the Garden Level. New opening has been formed between proposed Kitchen & Dining Room which will give a generous, light filled family space. Screed poured and first fix plumbing ongoing. The existing walls have been stripped to allow for damp proofing and insulation. Before and after images of chimney re-build […]
Tag: Victorian Renovation
Rostrevor Terrace Week 2 Progress
Week 1 & 2 progress Weeks 1 & 2 on site comprised Site clearance, formation of new openings, erection of scaffolding for roof, façade and chimney stack restoration works, internal demolitions to the lower ground floor comprising removal of floors, walls and ceiling finishes.